Tuesday, May 25, 2010




Outside walls are framed and up.

Thursday, May 20, 2010

Walls are being framed!

Thursday, May 13, 2010


The floor joists are almost all set now. We're seeing progress daily.

Tuesday, May 4, 2010

Backfill has been done and the materials for the framing is beginning to pile up on the site.

Thursday, April 22, 2010

Concrete finished.

Thursday, April 15, 2010

April 15, 2010




Wednesday, April 7, 2010

April 7, 2010. First post for the new building site for the Garden Valley District Library.